CCEA approves 3rd phase of PMGSY

Cabinet Committee on Economic Affairs (CCEA) chaired by the Prime Minister Narendra Modi has approved 3rd phase of Pradhan Mantri Gram Sadak Yojana (PMGSY) to consolidate 1,25,000 km of roads in the states.

Key Features of PMGSY-III Scheme

The 3rd phase of PMGSY (or PMGSY-III) involves consolidation of through routes and major rural links that connects habitations to Gramin Agricultural Markets (GrAMs), hospitals as well as Higher Secondary Schools.

Financial Implications-

Cost: An estimated cost of PMGSY-III would be Rs 80,250 crore over next five years out of which Central Share-Rs 53800 crore and State Share- Rs 26450 crore.

Fund: to be shared in ratio of 60:40 between Centre and State for all States except for 8 North Eastern and 3 Himalayan States (Jammu & Kashmir, Himachal Pradesh & Uttarakhand) for which it is 90:10.

Implementation-

Project Target period: 2019-20 to 2024-25.

Parameter for Road Selection: A candidate road selection is based on sum total of marks obtained by particular road on basis of parameters of population served, educational and medical facilities, market, etc.

Construction of Bridges: up to 200 m in Himalayan and NE States and 150 m in plain areas proposed from existing provisions of 100 m and 75 m in Himalayan and NE States and plain areas respectively.

Memorandum of Understanding: States shall be asked to enter into MoU before launching of PMGSY-III in concerned State for providing adequate funds for maintenance of roads constructed under PMGSY post 5-year construction maintenance period.

Background

PMGSY-III scheme was announced by Union Finance Minister in Budget Speech for year 2018-19.

CCEA in its meeting held on 9th August, 2018 approved continuation of PMGSY-I & PMGSY-II beyond 12th FYP Plan and covering of balance eligible habitations under PMGSY-I by March 2019, PMGSY-II, and habitations under identified LWE blocks (100-249 population) by March 2020.

Progress under PMGSY: Under the scheme a total of 5,99,090 Km road length has been constructed since inception till April, 2019 inclusive of PMGSY-I, PMGSY-II and Road Connectivity Project for Left Wing Extremism Area (RCPLWEA) Scheme.